How to create statis baseline start and finish date columns that won't change

Hi

I have a plan which has actual start and finish date columns based on predecessors and successors. Since a project may run for a few years I wanted to add baseline start and finish date columns so user can easily spot delays, shifts in timing. This should be easy, but haven't worked out how to do it. I tried just copy paste the actuals into the baseline columns. However they are then linked to the predecessors and successors and change along with the actuals. Is there a way just to copy the values as static dates, or a better way to do this? Please note I'm relatively new to project and couldn't find solution in online help/books.

Many thanks, Ross

J
Jaimin Shah 👤 Member for 13 years 1 month

The standard practice is to save baseline after your schedule is perfect, before puting any actual.

Then u can update actuals and monitor the difference between plan v/s actual.

After the completion of project upto some %ge, u fill that there are noticable changes, which need to be edited in plan itself (like addition of scope or like modification / revision / rework), than you can copy paste actuals as baseline2 with neccessory additions.

Save baseline2 and than again start putting actuals. Monitor plan v/s actuals again...

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts