I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!
So, Any body have an Idea about please share it.
Regards.
Dear Planners;
I'm worried about the Duration % complete on summary tasks on MS Project programme calculation!
So, Any body have an Idea about please share it.
Regards.
Thank you Ali for the confirmation.
% complete on summary task are calculated by simple aritmetic average , assume you have 2 task under summary task , which has 10 and 20 days durations and %40 and %50 completes , % complete calculates such as (40*10)+(50*20)/30