Baselines on MSP

Hi Guys,

 

Question and apologies if this is an easy one.  i have 7 updated MSP programmes for a project, December through to June.  The Critical Path is through the same section of works for each month.  I want to set the previous month as the basline for each month and also maybe set December as the Baseline for June to show As Planned Vs As built.

How do i do this, ie set a different MSP programe as a baseline. Is it a problem that as the project progress more detail was added into the Programme, more activities, therefore act ID 43 will not match with Activity ID 43 for a later programme.

 

Thanks in advance.

I
Ismet Kocaman 👤 Member for 16 years 4 months

You can test it as follows:

- Just save 2 baselines: Baseline 1 and Baseline 2.

- Add any Project field for both Baseline 1 and Baseline 2 (e.g. Baseline 1 Duration and Baseline 2 Duration) to the table (e.g. Entry table of the Gantt Chart View).

- Practice and see how the fields change as you modify the task list by deleting, inserting, moving task lines.

Regards,

Ismet

J
John Kelly 👤 Member for 15 years

Apologies saved two of these by accident!!! (won't happen again Mike, just realised that saving actually posts it!!!)

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts