Variance Report in MS Project

R
Raul Santos 👤 Member for 16 years 7 months

I need to compare the changes between this period (this month) and the previous period (last month) in order to see slippages in the schedule. I will appreciate any support on this matter.

D
Darren Kosa 👤 Member for 18 years 3 months

Hi Raul,

Have you thought of using Interim Baselines?

Saving an Interim Baseline every month is a pretty easy way to show slippage.

Regards,

Darren Kosa