Actual % Complete

A
Ahmed KHR 👤 Member for 15 years 6 months

Dear all,

 

How can I introduce actual % complete to MS Project to get Duration delay?

 

Regards

K
Kumar Baiju 👤 Member for 15 years 3 months

Hi Alll

      I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs
   
K
Kumar Baiju 👤 Member for 15 years 3 months

Hi Alll

      I am new for this forum and i ahve no idea how can add any question to this. I have one question about the actual duratin in MS project-2003. i am using 24 hous calander. whan i updated my actual duration Eg 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. i cannot understand why in summary it comes only nearly one fourth duration

4.83 Hrs 2.41 Hrs
20 Hrs 10 Hrs
   
T
Trevor Rabey 👤 Member for 20 years 6 months

I know what % Complete is. It is just the actual duration divided by the total duration. So if you have a 10 day task and 6 days of actual duration and 4 days of remaining duration, then % Complete = 60%. But I don't know what you mean by "duration delay". What is it?

D
Darren Kosa 👤 Member for 18 years 3 months

Hi Ahmed,

This is probably a very simplistic solution, but have you tried experimenting with 'Types' and using fixing work / effort driven when updating actuals?

Regards,

Darren

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts