BCWP is lower than expected.......my SPI is below 1

S
Sam Tan 👤 Member for 15 years 7 months

Hello,

i'm trying to do EVM for a project for the month of November.  i filled in the actual hours for all my tasks for the month.....(for all the people), and put zero actuals when that task was not worked on but was scheduled to be worked on.

now, when i'm looking at my "Task sheet", i see the following.  (i'm concerned about the second major tasks in bold).  I know we're not behind schedule but how can i increase my BCWP to artificially increase my SPI?

 

 

BCWS
BCWP
ACWP
SV
CV

$0.00
$0.00
$0.00
$0.00
$0.00

$60,841.86
$60,670.96
$48,947.07
($170.89)
$11,723.89

$45,791.52
$38,638.56
$28,839.89
($7,152.96)
$9,798.67

$0.00
$0.00
$0.00
$0.00
$0.00

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts