BCWP is lower than expected.......my SPI is below 1

S
Sam Tan 👤 Member for 15 years 6 months

Hello,

i'm trying to do EVM for a project for the month of November.  i filled in the actual hours for all my tasks for the month.....(for all the people), and put zero actuals when that task was not worked on but was scheduled to be worked on.

now, when i'm looking at my "Task sheet", i see the following.  (i'm concerned about the second major tasks in bold).  I know we're not behind schedule but how can i increase my BCWP to artificially increase my SPI?

 

 

BCWS
BCWP
ACWP
SV
CV

$0.00
$0.00
$0.00
$0.00
$0.00

$60,841.86
$60,670.96
$48,947.07
($170.89)
$11,723.89

$45,791.52
$38,638.56
$28,839.89
($7,152.96)
$9,798.67

$0.00
$0.00
$0.00
$0.00
$0.00

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts