I dont know what you mean by "as-built date" since this is not the name of any field in MSP. I guess you mean Actual Finish, maybe.
Try this.
You have a 10 day task, planned to start (ie has an early start date) on Monday 23rd August. Lets say that it is Sunday 22nd August when you plan it so you also save a baseline.
At the end of the following Monday (30/8)you decide to measure the progress and update the task. So 30/8 is the Status Date and this is set in Project, Project Information.
You wil want to see your baseline bars so you should switch to the Tacking Gantt view.
You can show the Status Date as a vertical line on the chart with Format, Gridlines.
The first thing to do is to establish the Actual Start date of the task. Was it 23/8 or some later date between 23/8 and 30/8? Whatever it was, it goes into the Actual Start field which is available in the Tracking Table.
The next thing is to establish the Actual Duration.
If the task started on 23/8 and every day up to 30/8 was a day of actual duration, then the answer is 6 and this goes in the Actual Duration field, also in the Tracking Table.
If the task was under way or in progress continuously every day from the Actual Start, then you can use the "update as scheduled" button on the tracking toolbar to count the days for you. If the task started later than 23/8 and/or the task was interupted then Actual Duration is something less than 6.
After you fill in the Actual Start and Actual Duration, you may have unused or planned duration to the left of the Status Date. For example, if the task started on 23/8 and had 2 days of Actual Duration, there will be 8 days of Remaining Duration, but 4 of them will be in the past relative to the Status Date. To move them into the future, because you cannot plan to do something in the past, click on the 3rd button on the Tracking Toolbar, "Reschedule Work". I have always thought that this button should be called "Reschedule Duration" because that is what it does, but, hey, so what. The last step is to decide whether you still estimate that the task has 8 days of Remaining Duration. You might want to re-estimate it up or down.
Remember:
Do not type in % Complete - MSP works this out for you.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Stuart,
I dont know what you mean by "as-built date" since this is not the name of any field in MSP. I guess you mean Actual Finish, maybe.
Try this.
You have a 10 day task, planned to start (ie has an early start date) on Monday 23rd August. Lets say that it is Sunday 22nd August when you plan it so you also save a baseline.
At the end of the following Monday (30/8)you decide to measure the progress and update the task. So 30/8 is the Status Date and this is set in Project, Project Information.
You wil want to see your baseline bars so you should switch to the Tacking Gantt view.
You can show the Status Date as a vertical line on the chart with Format, Gridlines.
The first thing to do is to establish the Actual Start date of the task. Was it 23/8 or some later date between 23/8 and 30/8? Whatever it was, it goes into the Actual Start field which is available in the Tracking Table.
The next thing is to establish the Actual Duration.
If the task started on 23/8 and every day up to 30/8 was a day of actual duration, then the answer is 6 and this goes in the Actual Duration field, also in the Tracking Table.
If the task was under way or in progress continuously every day from the Actual Start, then you can use the "update as scheduled" button on the tracking toolbar to count the days for you. If the task started later than 23/8 and/or the task was interupted then Actual Duration is something less than 6.
After you fill in the Actual Start and Actual Duration, you may have unused or planned duration to the left of the Status Date. For example, if the task started on 23/8 and had 2 days of Actual Duration, there will be 8 days of Remaining Duration, but 4 of them will be in the past relative to the Status Date. To move them into the future, because you cannot plan to do something in the past, click on the 3rd button on the Tracking Toolbar, "Reschedule Work". I have always thought that this button should be called "Reschedule Duration" because that is what it does, but, hey, so what. The last step is to decide whether you still estimate that the task has 8 days of Remaining Duration. You might want to re-estimate it up or down.
Remember:
Do not type in % Complete - MSP works this out for you.
You cannot plan to do something in the past.
You cannot make progress in the future.
Hope this helps.