Re-baselining a schedule in MSP

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hi there,

it is not possible that you cannot re-baseline a project: when you are re-baselining a project, you receive a message asking if you want to replace the existing baseline; click "Yes" to save a new baseline and replace the existing one

this is true for any MS Project release since the beginning.

Alexandre

D
Darren Kosa 👤 Member for 18 years 4 months

Hi Peace,



Could you be a bit more specific and provide us with a more detail?



What happens exactly when you try to re-basline? Do you get any error messages? How did you baseline the project in the first instance?



Regards,



Darren