AC in Earned Value Analysis

M
Mike Roberts 👤 Member for 16 years 4 months

Thanks Trevor for your help! I am aware of this option. My problem is MSP for Actual Cost of Work Performed (ACWP) calculates something different from Actual Cost field (AC) when you input actual costs manually rather than giving MSP calculates them using resource rates.


T
Trevor Rabey 👤 Member for 20 years 7 months

In Tools, Options, Calculation is an option "Actual Costs are always calculated by Microsoft Project"



Of this option is checked, then you cannot input Actual Cost (usually in the Tracking Table). It will be "greyed out".

But if the Actual Cost of a task was different from this, then you turn off the option and will find that you can input the Actual Cost.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts