Critical bar

M
Mike Testro 👤 Member for 20 years 5 months

Come on Guys



Just a simple answer on one side of the paper will do.



Best regards



Mike Testro



PS Hi Ismet



Welcome to PP - now that you have met up with Rafael it seems that you speak the same language in planning terms - praise be that you express it in English.

R
Rafael Davila 👤 Member for 22 years 3 months

Or perhaps?



MS Bar Styles



Look at the range of the float bar I defined it not the usual, from ES instead of from EF.



Or maybe?



MS Split

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dan



I think you mean you have put some progress on the bar and it is split at the progress line.



In which case only the work still in progress should show critical.



Surely MSP does that automatically.



Best regards



Mike Testro

D
Dan Mårtensson 👤 Member for 16 years 4 months

Hello Ismet



I know how to display the critical bars in the gantt chart. But what I seek is the function that Primavera has, the bar can show both blue and red (in this case).



Thanks



Regards



Dan




I
Ismet Kocaman 👤 Member for 16 years 3 months

Dan,



You can change the current view (I suppose it is the Gantt Chart view that you are currently working on) to display critical task bars in red. e.g. use Tracking Gantt View

on the View menu.



Regards,

Ismet Kocaman

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts