in MS Project, the baseline is a part of the projet
Go to Tools, Tracking, Save Baseline (Define Baseline in MSP 2007),
then look at every baseline in the drop down list (from Baseline to Baseline 10): a already saved baseline should be documented with the date it was saved
BTW, to save a baseline means that the scheduling fields (Duration, Start, Finish, Work, Cost) were pasted in "Baseline xx" fields; it is very different from P3 where the baseline is another project.
Member for
22 years 9 monthsRE: check if project saved as baseline
Faisal,
in MS Project, the baseline is a part of the projet
Go to Tools, Tracking, Save Baseline (Define Baseline in MSP 2007),
then look at every baseline in the drop down list (from Baseline to Baseline 10): a already saved baseline should be documented with the date it was saved
BTW, to save a baseline means that the scheduling fields (Duration, Start, Finish, Work, Cost) were pasted in "Baseline xx" fields; it is very different from P3 where the baseline is another project.
Hope this helps,
Alexandre