Thank you to everyone who replied. Following your advice I managed to squeeze the Gannt chart onto one page. It still wanted to print more, but I prevented them by just printing page 1 only.
this is a well known bug that appeared in MS Project 98 or 2000 and that MS is reluctant to reckognize
as far I as know, there is very little that can be done to correct the situation; sometime, the offending blank page disappears when you check-out the Fit timescale to Page in Preview, Setup, Display ( I am transtlating freely from French), sometime it does not do anything
What you describe is fairly common but there are a number of probable causes. Hopefully one of these suggestions will give you a solution.
Change the date range
(File > Print) in the Timescale options either select the All radio button or select the Dates radio button and change the Finish date so that it’s after the end date of the project.
Change the Gantt Chart timescale to fit on A1 before you print
(Format > Timescale) adjust the timescale on whatever Tier tabs you use (i.e. if you use days change to weeks, if you use weeks change to months). Then use the print preview to see if it fits on one page (File > Print Preview).
Only print the first page
(File > Print) in the Print Range options select the Page(s) radio button and then only choose the print range From: 1 To: 1. this should only print the first page.
You can also use Page Setup if none of the above fixes your problem.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thank you to everyone who replied. Following your advice I managed to squeeze the Gannt chart onto one page. It still wanted to print more, but I prevented them by just printing page 1 only.
Hello all,
this is a well known bug that appeared in MS Project 98 or 2000 and that MS is reluctant to reckognize
as far I as know, there is very little that can be done to correct the situation; sometime, the offending blank page disappears when you check-out the Fit timescale to Page in Preview, Setup, Display ( I am transtlating freely from French), sometime it does not do anything
just be patient, its only MS Project...
Alexandre
Hi Terry,
What you describe is fairly common but there are a number of probable causes. Hopefully one of these suggestions will give you a solution.
Change the date range
(File > Print) in the Timescale options either select the All radio button or select the Dates radio button and change the Finish date so that it’s after the end date of the project.
Change the Gantt Chart timescale to fit on A1 before you print
(Format > Timescale) adjust the timescale on whatever Tier tabs you use (i.e. if you use days change to weeks, if you use weeks change to months). Then use the print preview to see if it fits on one page (File > Print Preview).
Only print the first page
(File > Print) in the Print Range options select the Page(s) radio button and then only choose the print range From: 1 To: 1. this should only print the first page.
You can also use Page Setup if none of the above fixes your problem.
Regards,
Darren
Have you tried reducing the Size % in the timescale data when you right click the dates at the top of the Gantt?
You can fit to one page also (page setup) and or opt to only print the timescales that you need when you press file print (bottom corner)