I personally am very familiar with EV but I understand what you mean about trying to push any excess and complicated metrics reporting onto the program team.
The point I was trying to get at is before attempting to start using it for the Program I work on if there were any shortfalls.
Having gone through your earlier posts, a lot of the suggestions have credibility in theory but from experience, the simplest form is always the best as we are keeping the calculations to a minimum as these things tend to go off on a tangent with a lot of backtracking which can be painstaking work!
Martin,
A lot of what Darren has suggested is sufficient if you are a power user as you can get a grasp on what you are looking for...however, I find it for those who are not familiar with the earned value conundrum, sticking to the simplest version until you are confident enough to explain your analysis in layman terms to your superiors as they do not want to get bogged down in the "terminology".
Chatting with some EV gurus today, I broached the subject of TSPI and was informed unequivocally that it can’t be calculated in the way I suggested. It would always equal 1 which kind of makes sense now I think about it.
Much better to use the method Phillip suggested in Post #2
So if you are halfway though a Project / CA / WP and the SPI is 0.90, then the SPI for the remainder of the Project / CA / WP would have to be 1.1.
Shouldn’t be a problem. In reality the net effect is neutral, it’s just a matter of preference.
If you think about it EAC is just BAC plus or minus any variance.
BCWS establishes the baseline, but it’s also the value of all work scheduled to be carried out in a given period of time. This can be cumulative or shown month-by-month.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Philip,
I personally am very familiar with EV but I understand what you mean about trying to push any excess and complicated metrics reporting onto the program team.
The point I was trying to get at is before attempting to start using it for the Program I work on if there were any shortfalls.
Maybe you are right and simplicity is key.
Thanks for your responses
Martin
All,
Sorry for not posting sooner!
Darren,
Having gone through your earlier posts, a lot of the suggestions have credibility in theory but from experience, the simplest form is always the best as we are keeping the calculations to a minimum as these things tend to go off on a tangent with a lot of backtracking which can be painstaking work!
Martin,
A lot of what Darren has suggested is sufficient if you are a power user as you can get a grasp on what you are looking for...however, I find it for those who are not familiar with the earned value conundrum, sticking to the simplest version until you are confident enough to explain your analysis in layman terms to your superiors as they do not want to get bogged down in the "terminology".
Lesson learned here...keep it simple!
Martin,
Chatting with some EV gurus today, I broached the subject of TSPI and was informed unequivocally that it can’t be calculated in the way I suggested. It would always equal 1 which kind of makes sense now I think about it.
Much better to use the method Phillip suggested in Post #2
So if you are halfway though a Project / CA / WP and the SPI is 0.90, then the SPI for the remainder of the Project / CA / WP would have to be 1.1.
Regards,
Darren
Martin,
If you think of it another way, EV is all about analysing and forecasting using trends.
All you really need to decide is do you forecast what you actually think is remaining, or what is remaining in the budget.
Regards,
Darren
Martin,
Shouldn’t be a problem. In reality the net effect is neutral, it’s just a matter of preference.
If you think about it EAC is just BAC plus or minus any variance.
BCWS establishes the baseline, but it’s also the value of all work scheduled to be carried out in a given period of time. This can be cumulative or shown month-by-month.
Regards,
Darren
Thanks for your responses
Darren I am unsure about the EAC calculation as the BCWS would only calculate as far as the baseline.
Hi Martin,
It’s been a while since I looked at any advanced formula. As I recall you can have TCPI (BAC) and TCPI (EAC).
I can’t see any reason why you couldn’t therefore use either TSPI (BAC) or TSPI (EAC).
TSPI could then be calculated by:
(BAC – BCWP) / (BAC – BCWS)
Or
(BAC – BCWP) / (EAC – BCWS)
You could probably even use IEAC in place of EAC... although youd have to test it out just to be sure.
Regards,
Darren
Hi Martin,
In theory, it would give that answer.
But a better option would be the remaining duration/SPI as this would give a more realistic forecast.
Regards,
Philip