I have used Microplanner for several years. I can understand your comment about the use of the tool, and I can add that I found Open Plan and Primavera particularly difficult to use after using Microplanner.
It is just what you’re used to using.
I use Primavera version 5 through to 6.1 on a daily basis at this time, depending on what project I’m working on.
I must say that I do find myself using the trial version of Microplanner which I have as a way of checking the answer I get from Primavera.
Since using Primavera I have not even considered using the resource levelling function as the answers you get are confusing to say the least, I do have a paper I wrote on the results of resource analysis within P5 if you would like a copy it can be found at www.eh.com.au in the technical papers section.
Quite simply the algorithm in Microplanner which it uses to calculate the project forward and backward pass is far and away the most robust version of such a mathematical equation on the market. (My opinion only)
The resource analysis is the standard MO of the tool for either time limited and or resource limited. It can do a time only analysis but quite frankly why would you bother when you have a tool which can calculate a perfect resource profile. (Again - My opinion only)
I will say that there are a number of things that need to be considered when choosing your settings, BUT there are an infinitesimal amount of things that will cause you pain and grief using Microplanner. (Fact)
On the other hand there are so many bells and whistles in Primavera I have found that different users can get different information calculated at the same time in the same project using different settings, and when the project is closed and re-opened it is quite simply the luck of the draw as to which information would be stored. It is not related to who did what first and who closed the project first or anything I can find; it’s simply luck of the draw.
Microplanner simply operates on the KISS principle; it has a number of settings that provide a robust output which can be justified by analysis, without long periods of head scratching like other tools. (who shall remain nameless)
I also have a small presentation on the different features of Microplanner I once used (Many times) to purport the benefits of the system and show people how the information was used.
I also know that there used to be self paced CBT available for Microplanner which could be commercially available if you ask the right people?????
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Daniel,
I have used Microplanner for several years. I can understand your comment about the use of the tool, and I can add that I found Open Plan and Primavera particularly difficult to use after using Microplanner.
It is just what you’re used to using.
I use Primavera version 5 through to 6.1 on a daily basis at this time, depending on what project I’m working on.
I must say that I do find myself using the trial version of Microplanner which I have as a way of checking the answer I get from Primavera.
Since using Primavera I have not even considered using the resource levelling function as the answers you get are confusing to say the least, I do have a paper I wrote on the results of resource analysis within P5 if you would like a copy it can be found at www.eh.com.au in the technical papers section.
Quite simply the algorithm in Microplanner which it uses to calculate the project forward and backward pass is far and away the most robust version of such a mathematical equation on the market. (My opinion only)
The resource analysis is the standard MO of the tool for either time limited and or resource limited. It can do a time only analysis but quite frankly why would you bother when you have a tool which can calculate a perfect resource profile. (Again - My opinion only)
I will say that there are a number of things that need to be considered when choosing your settings, BUT there are an infinitesimal amount of things that will cause you pain and grief using Microplanner. (Fact)
On the other hand there are so many bells and whistles in Primavera I have found that different users can get different information calculated at the same time in the same project using different settings, and when the project is closed and re-opened it is quite simply the luck of the draw as to which information would be stored. It is not related to who did what first and who closed the project first or anything I can find; it’s simply luck of the draw.
Microplanner simply operates on the KISS principle; it has a number of settings that provide a robust output which can be justified by analysis, without long periods of head scratching like other tools. (who shall remain nameless)
I also have a small presentation on the different features of Microplanner I once used (Many times) to purport the benefits of the system and show people how the information was used.
I also know that there used to be self paced CBT available for Microplanner which could be commercially available if you ask the right people?????
Andy
Daniel
Forgot to ask for your e-mail address
Raf
Absolutely
Obviously you are more Gantt oriented than Logic networks
I will get John Cornish to Ring you seeing as how you are in the UK
Raf Dua
MPI Pty Ltd
+61 418 53 1111
[email protected]