Sounds like you’ve already managed to create a calendar, but I’ll start from the beginning anyway.
Create a Calendar
1. Tools > Change Working Time
2. Click the New button, select the make copy of radio button and choose Standard from the drop-down menu. Choose an appropriate name for the new calendar (I’ll use Possession in this example) and click the OK button.
3. With the new ‘Possession’ Calendar selected, scroll down to November and select the 15th.
4. Select the Nondefault working time radio button delete the times displayed in the From & To cells and add 23:00 in the From cell and 00:00 in the To cell.
5. Select the 16th and repeat step 4, but this time add 00:00 in the From cell and 15:00 in the To cell.
6. Click the OK button.
Using the Possession Calendar
1. Using the Gantt Chart view, add a task to the schedule that will represent the possession.
2. Display the Task Information dialog box for your new task (Project > Task Information) and select the Advanced tab.
3. Select Possession from the Calendar drop-down menu and click the OK button.
4. Using precedence logic or date constraints to make the start of your Possession task the 15th November.
5. Set the Duration of the task to 16h.
The task should now start 23:00 on the 15th and finish 15:00 on the 16th, if it doesn’t then just adjust the hours.
You are correct in thinking that the default timescale for a MS Project day is 8hrs, so by using days as a Duration unit your finish time will be too early. By using a new calendar and hours instead of days, you can bypass the default calendar options.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Darren,
Thank you very much for taking the time to explain. I will try that today.
Thanks,
Stuart
Hi Stuart,
Sounds like you’ve already managed to create a calendar, but I’ll start from the beginning anyway.
Create a Calendar
1. Tools > Change Working Time
2. Click the New button, select the make copy of radio button and choose Standard from the drop-down menu. Choose an appropriate name for the new calendar (I’ll use Possession in this example) and click the OK button.
3. With the new ‘Possession’ Calendar selected, scroll down to November and select the 15th.
4. Select the Nondefault working time radio button delete the times displayed in the From & To cells and add 23:00 in the From cell and 00:00 in the To cell.
5. Select the 16th and repeat step 4, but this time add 00:00 in the From cell and 15:00 in the To cell.
6. Click the OK button.
Using the Possession Calendar
1. Using the Gantt Chart view, add a task to the schedule that will represent the possession.
2. Display the Task Information dialog box for your new task (Project > Task Information) and select the Advanced tab.
3. Select Possession from the Calendar drop-down menu and click the OK button.
4. Using precedence logic or date constraints to make the start of your Possession task the 15th November.
5. Set the Duration of the task to 16h.
The task should now start 23:00 on the 15th and finish 15:00 on the 16th, if it doesn’t then just adjust the hours.
You are correct in thinking that the default timescale for a MS Project day is 8hrs, so by using days as a Duration unit your finish time will be too early. By using a new calendar and hours instead of days, you can bypass the default calendar options.
Regards,
Darren