Exporting to Excel

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Dave,

in MS Project 2007, "Export timescaled data to Excel" was replaced by some "Visual Report"; open Reports, Visual Reports, and you will find what you need (sorry, I do not have MSP 2007 with me, I cannot be more directive)

Hope it helps,

Alexandre

P
Paul Harris 👤 Member for 25 years 2 months

Use the Analysis Toolbar.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts