track a project
Forum Sponsor
Top Posters
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Faisal,
Here’s what I would suggest...
Reschedule tasks that haven’t started
Tasks should be automatically rescheduled if the precedence logic is correct, if it isn’t try using lag times or reviewing the logic
Let MS Project calculate the % Complete
View > Table > Tracking
By entering actual start, duration / work and remaining duration / work MS Project will calculate the % Complete(s)
How do i know whether my project is on schedule or not
Use the status date and progress line as an aide and check against baseline.
Hope this helps.
Regards,
Darren
i want to know three things
1)Reschedule tasks that haven’t started
2)Let MS Project calculate the % Complete(s)
3) how do i know whether my project is on schedule or not
Hi Faisal,
That’s a bit of a tricky question, you can use MS Project in many ways to track progress.
I’ll try and give you the 5 cent tour and then hopefully you can refine your question a little more.
1) Baseline the project (effort and duration)
2) Track actual start dates and actual effort / duration and remaining effort / duration
3) Reschedule tasks that havent started
4) Let MS Project calculate the % Complete(s)
Regards,
Darren