Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Darren,colin and Pinan,
Thank you very much for the tips, this is exactly what i needed , same view of P3.
regards
deb
Hi Deb,
Another variation for seeing predecessors / successors in a visual format... as if you need another ;o)
Window > Split > and then click anywhere in the Task Form
Then you need View > More Views > Relationship Diagram
Whenever you select a task in the Task Entry you will also get a graphical representation in the Split Window.
Might be a bit meaningless for most, but it’s helpful for some.
Regards,
Darren
Hi Pranab
Try Window / Split
Right click on the bottom window - select Predecessors & Successors
This will give you the Task Form
For the Task Details Form -
(make sure you have clicked in a field in the bottom pane)
View / More views
Select Task Details Form
Apply
(Note-You can set up a custom view which will retain this view)
Is this what youre after
Colin
Dear friend
Double click on any task a tab will appear go to predessor and u can see it
Regards
Faisal
In Task Information only, or use Column..