bingo,
Worked man, thanks alot. But why didnt it work. I set it to fixed duration but just cos I didnt put 100%units it didnt.
Cheers man
thanks man will try it out asap.
cheers
Set the Task Duration to 5 Days.
Assign the 2 Resources at 100%.
Set the Task Type to Fixed Duration, effort driven on.
Switch to the Task Usage View.
Type in 14 hours Work for the Piping Engineer.
Type in 16 hours Work for the Mechanical Engineer.
The Duration will not change while you make the changes.
MSP will spread the hours for each Resource over the 5 Days, 2.8 hours/Day and 3.6 Hours/Day respectively.