Thanks for the reply, sorry Im confusing things and I dont even know how, Ive just gone back to check what Ive done and yep, following your guide gives the right result!!
I was trying to show the same without Task 3 - ie is there any way to show in MSP a floating task whos start date is driven by Task 1 but whos end date is driven by elapsed time (a date) rather than task duration i.e avoiding the need to add Task 3 as a successor. ie the delivery window is say 80days but the delivery process is 60days.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Sara,
Sounds like what you’re after is a ’Hammock’ task.
If it is, be careful how often you use them as they have been known to corrupt project files if you have too many.
Have a look and see if this fits the bill.
http://support.microsoft.com/kb/141733
Regards,
Darren
Hi Darren,
Thanks for the reply, sorry Im confusing things and I dont even know how, Ive just gone back to check what Ive done and yep, following your guide gives the right result!!
I was trying to show the same without Task 3 - ie is there any way to show in MSP a floating task whos start date is driven by Task 1 but whos end date is driven by elapsed time (a date) rather than task duration i.e avoiding the need to add Task 3 as a successor. ie the delivery window is say 80days but the delivery process is 60days.
Thanks
Hi Sara,
It seems a little strange that the end milestone date would move the start date of Task 1, if everything is linked correctly.
I’m assuming that you have already set the project start date and that the activities are being driven by precedence rather that constraints.
I’m also assuming that the schedule looks something like this
Task 1 Duration 1d and has a FS relationship with Task 2
Task 2 Duration 60d and has a FS relationship with Task3
Task 3 Duration 0d and has a FNET constraint 04/08/08
Task 1 Starts 15/04/08 Finishes 15/04/08
Task 2 Starts 16/04/08 Finishes 10/07/08 (Inc. Bank Holidays)
Task 3 Starts 04/08/08 Finishes 04/08/08
Another question is, do you have the ’Tasks will always honor their constraint dates’ checkbox ticked? (Tools > Options > Schedule Tab)
Regards,
Darren