Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2008-04-13 10:02 Permalink RE: Need to show day and night time activities Amit, 1. Calendar: Tools, Change working time, Create 2. Apply calendar to tasks: Project, Task Information, Advanced, Calendar 3. Filter: Project, Filtered for, More filters, New; Task calendar equals to Night Time Hope this helps Alexandre Member for 17 years 7 months Member for 17 years 7 months Submitted by Amit Raisinghani on Sun, 2008-04-13 08:48 Permalink RE: Need to show day and night time activities Thanks Alexandre for your reply. Could u please run me through, how i should create a new calendar and filter it out please. Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2008-04-13 08:05 Permalink RE: Need to show day and night time activities Amit, Create a new "Night time" calendar, and apply to activities that occur during the night; then create a filter where calendar = "night time" Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2008-04-13 10:02 Permalink RE: Need to show day and night time activities Amit, 1. Calendar: Tools, Change working time, Create 2. Apply calendar to tasks: Project, Task Information, Advanced, Calendar 3. Filter: Project, Filtered for, More filters, New; Task calendar equals to Night Time Hope this helps Alexandre
Member for 17 years 7 months Member for 17 years 7 months Submitted by Amit Raisinghani on Sun, 2008-04-13 08:48 Permalink RE: Need to show day and night time activities Thanks Alexandre for your reply. Could u please run me through, how i should create a new calendar and filter it out please.
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Sun, 2008-04-13 08:05 Permalink RE: Need to show day and night time activities Amit, Create a new "Night time" calendar, and apply to activities that occur during the night; then create a filter where calendar = "night time" Alexandre
Member for
22 years 9 monthsRE: Need to show day and night time activities
Amit,
1. Calendar: Tools, Change working time, Create
2. Apply calendar to tasks: Project, Task Information, Advanced, Calendar
3. Filter: Project, Filtered for, More filters, New; Task calendar equals to Night Time
Hope this helps
Alexandre
Member for
17 years 7 monthsRE: Need to show day and night time activities
Thanks Alexandre for your reply. Could u please run me through, how i should create a new calendar and filter it out please.
Member for
22 years 9 monthsRE: Need to show day and night time activities
Amit,
Create a new "Night time" calendar, and apply to activities that occur during the night; then create a filter where calendar = "night time"