Hours and % effort at resource assignment

A
Andrew Dick 👤 Member for 19 years 4 months
N
Niek Zonneveld 👤 Member for 21 years 3 months

Andrew,



The first thing I would normally check is if the assignment work has been edited. You can do this by looking at the indicator column in the default assignment view, or by double clicking on the assignment.



If the work contour is not flat (but contoured, for instance) the regular schedule equation (D=W/U) no longer holds.



Hope this helps,



Niek.