Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2009-03-30 13:06 Permalink RE: Effort driven yâ moutaz, whatever you are doing in msp options, it is for the future only for existing tasks, select all the tasks, click project, task information, advanced, then check out the "effort driven" box bqa 3la kheir Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2009-03-30 13:06 Permalink RE: Effort driven yâ moutaz, whatever you are doing in msp options, it is for the future only for existing tasks, select all the tasks, click project, task information, advanced, then check out the "effort driven" box bqa 3la kheir
Member for
22 years 9 monthsRE: Effort driven
yâ moutaz,
whatever you are doing in msp options, it is for the future only
for existing tasks, select all the tasks, click project, task information, advanced, then check out the "effort driven" box
bqa 3la kheir