MSP 2007 to Primavera
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
thanks a lot guys,
I have found a conversion utility from one of the earlier posts. Have a look.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=7868
Cheers and thanks for the help
There is a technical article on my web site that may help.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Kartik,
Microsoft does not maintain the MPX file format since MSP 2000; to "export" a project plan, use the File, Save As command and save a MS Excel file.
If you have a valid serial number, you will be able to download from www.primavera.com a bunch of MS Excel files that make it easier to migrate plans from MSP to P3.
Look carefully at the scheduling options, that are pretty different from one app to the other
Alexandre