i knw you have solved this problem but as soon as wrote this:
> If I have a task that runs from 09:00 on a monday to > >09:00 on a Tuesday
I knew immediately something was wrong as 1 day activity by default would start at 8am and finish at 5pm. So assuming you were using days then this impled you had a 24 hour calendar.
To resolve this using a 24 hour calendar then the start should be 0:00 and not 9am.
James,
Calendar option "Default start time" MUST BE coherent with the "opening hour" of a standard day as defined in the calendar dialog box;
i.e. if you define the standard day as "8:00 - 12:00 and 13:00 - 17:00", you have to enter 8:00 and 17:00 as default start and default end time in the calendar options;
also, as changing these settings after the project is built will NOT change the project start date-and-time, yu should go to Project, Project infos, display the time with the date and make sure the project starts at the beginning of the day and not later.
Cheers,
Alexandre
Actually I take it all back it was down to the Options -> calendar settings. Id set the default start & end times to 00:00 as i was using a 24 hour calendar. It would appear that for whatever reason project doesnt like this and is much happier when the default start and end times were set to 8:00 and 17:00 respectively...
Its very strange I have looked through the hours etc and it doesnt seem to be the cause.
If I have a task that runs from 09:00 on a monday to 09:00 on a Tuesday the block on the gantt chart is displayed just for the whole of Tuesday, even thought the majority of the work is to occur on the Monday.
I wonder whether it may just be a setting somewhere that is incorrect? Is there anyway to reset all of Microsoft Projects settings back to default incase Ive altered something I shouldnt have done?
I havent had this problem but I would check the hours. It may be such that you are starting the activity at 6pm and not 8am or 9am. So go to options and change date format to dd/mmm/yy:hh and confirm the times.
Even if you are planning by days underneath msp still plans by the hour but the formatting cuts the hours off. I have seen a plan where they had played around with the no. of hours per days and 4 days of work gave them 5 or something.
Another possibility may be problems with start milestones and finish milestones. Having the hours on and changing to finish milestones you may find the solution.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Jmaes,
i knw you have solved this problem but as soon as wrote this:
> If I have a task that runs from 09:00 on a monday to > >09:00 on a Tuesday
I knew immediately something was wrong as 1 day activity by default would start at 8am and finish at 5pm. So assuming you were using days then this impled you had a 24 hour calendar.
To resolve this using a 24 hour calendar then the start should be 0:00 and not 9am.
James,
Calendar option "Default start time" MUST BE coherent with the "opening hour" of a standard day as defined in the calendar dialog box;
i.e. if you define the standard day as "8:00 - 12:00 and 13:00 - 17:00", you have to enter 8:00 and 17:00 as default start and default end time in the calendar options;
also, as changing these settings after the project is built will NOT change the project start date-and-time, yu should go to Project, Project infos, display the time with the date and make sure the project starts at the beginning of the day and not later.
Cheers,
Alexandre
Actually I take it all back it was down to the Options -> calendar settings. Id set the default start & end times to 00:00 as i was using a 24 hour calendar. It would appear that for whatever reason project doesnt like this and is much happier when the default start and end times were set to 8:00 and 17:00 respectively...
Thank you for your help!
Thanks for that.
Its very strange I have looked through the hours etc and it doesnt seem to be the cause.
If I have a task that runs from 09:00 on a monday to 09:00 on a Tuesday the block on the gantt chart is displayed just for the whole of Tuesday, even thought the majority of the work is to occur on the Monday.
I wonder whether it may just be a setting somewhere that is incorrect? Is there anyway to reset all of Microsoft Projects settings back to default incase Ive altered something I shouldnt have done?
Many Thanks
James
I havent had this problem but I would check the hours. It may be such that you are starting the activity at 6pm and not 8am or 9am. So go to options and change date format to dd/mmm/yy:hh and confirm the times.
Even if you are planning by days underneath msp still plans by the hour but the formatting cuts the hours off. I have seen a plan where they had played around with the no. of hours per days and 4 days of work gave them 5 or something.
Another possibility may be problems with start milestones and finish milestones. Having the hours on and changing to finish milestones you may find the solution.