Progress Line

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Jaco,

I ahd in mind that it was possible for MSP to display the progress line ahead of schedule; my mistake, I made the confusion with Sciforma Project Scheduler.

Look at the following page for a good example of how to use the progress lien:

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=595



As per the discussion on the following page, MS Project is RIGHT when not displaying the progress line ahead of schedule; there is the way of setting up the options if you want to display the p-line:

http://www.mcse.ms/message2168898.html



I hope it helps

Alexandre

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts