Progress Line

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Jaco,

I ahd in mind that it was possible for MSP to display the progress line ahead of schedule; my mistake, I made the confusion with Sciforma Project Scheduler.

Look at the following page for a good example of how to use the progress lien:

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=595



As per the discussion on the following page, MS Project is RIGHT when not displaying the progress line ahead of schedule; there is the way of setting up the options if you want to display the p-line:

http://www.mcse.ms/message2168898.html



I hope it helps

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts