it is possible to assigne resources the way you want, but I would suggest you dont and create two activities instead
I assume that the 2 or 3 carpenters are working full time
1. set the activity type as Fixed Duration (Activity Info, Advanced, Activity Type)
2. Display the Task Usage View
3. Assign TWO carpenters to the task
4. browse the task in the right pane of the screen until you reach day 6
5. change the amount of work from 14h (or 2d) to 21h (or 3d)
6. do the same until day 10.
Thats all, hombre
Alexandre