Assign Resources

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Pacifico,

it is possible to assigne resources the way you want, but I would suggest you don’t and create two activities instead

I assume that the 2 or 3 carpenters are working full time

1. set the activity type as Fixed Duration (Activity Info, Advanced, Activity Type)

2. Display the Task Usage View

3. Assign TWO carpenters to the task

4. browse the task in the right pane of the screen until you reach day 6

5. change the amount of work from 14h (or 2d) to 21h (or 3d)

6. do the same until day 10.

That’s all, hombre

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts