Assigning tasks to external suppliers

M
Mark Wells 👤 Member for 19 years 7 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Mark,

Check Tools, Resource leveling: you should set up "Manual".

It seems that Resource leveling is set up "Automatic": when you assign the same resource to an additional task that takes place at the same time, MSP reschedules the 2nd task after the 1st one to suppress overwork for the resource.

Cheers,

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts