Microsoft Project Member for 19 years 1 month Member for 19 years 1 month Submitted by ruben quintal on Sun, 2006-10-01 04:37 Permalink RE: Cost Scheduling hi Tolu, the cost driven schedule depends on the cost in computing its duration and activity sequencing, ei. duration(month) = activity cost/available monthly cashflow while duration driven schedules are more concern about the allowed duration or the required milestone or completion date. Log in or register to post comments
Member for 19 years 1 month Member for 19 years 1 month Submitted by ruben quintal on Sun, 2006-10-01 04:37 Permalink RE: Cost Scheduling hi Tolu, the cost driven schedule depends on the cost in computing its duration and activity sequencing, ei. duration(month) = activity cost/available monthly cashflow while duration driven schedules are more concern about the allowed duration or the required milestone or completion date.
Member for
19 years 1 monthRE: Cost Scheduling
hi Tolu,
the cost driven schedule depends on the cost in computing its duration and activity sequencing,
ei. duration(month) = activity cost/available monthly cashflow
while duration driven schedules are more concern about the allowed duration or the required milestone or completion date.