Resource units
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
hi Zhang ,
I think 16% is correct . My logic being a resource is available to us as per their base calanders , so it is with respect to that time available we should fill in the assignment units.
Any different Views ?
Its a complex issue.
In MSP there are 3 types of task, fixed duration, fixed work and fixed units. they act differently when assign/change recource.
for your question, use 50%, but maybe the duration will change based on task type.
Goto online help for details for task type,then try it