Thanks for your clarification….I understand slightly better (I think).
You’ve created three levels of coding, using “Outline Code” 1, 2 and 3. You have then applied the “Group By …” function to group the data according to Outline Code 1, 2 and 3. You are then trying to summarise and then filter-out certain summary bars. Please tell me if I’m talking rubbish.
Although I’ve almost never really used “Outline Code”, because it doesn’t really do anything for me, I believe that you can “Group By” any of the individual code levels. If you want, you can Group By only Outline Code 1, or Outline Code 2 or Outline Code 3….or any combination of them. If you would then like to “hide” or filter-out only certain summary bars, say, at Outline Code 3, but leave other summary-bars at Level 3, you will have to apply a filter only on those detailed asks that relate to the summary-bar that you would like to remove. If this is what you would like to do, then you can use a “Flag” (yes/no) against each of the detailed task. Apply the “Group By” function, then apply the filter to remove the relevant tasks. This should automatically remove the summary-bars that you wish not to see.
Thank you Mr. James Griffith and Mr. Christian Joseph orbe for valuable comments.
It took some time to reply due to professional commitments.sorry
When I reviewed my original question I found that the question doesn’t reflects what I intended to say.
I beg a pardon
Coming to the problem
I am a P3 user and forced to learn MSP due to third party involvement in a project Who makes plans in MSP
In P3 when we organize activities by WBS or activity code, we can show summary(Or Subtotal ) bar at all levels and have the option to show individual summary bars--- (“summary bar “not summarized bar,which we see when we collapse activities) Bars showing earliest start to latest finish date of group of activities
I was trying to do the same in MSP
I created outline codes 1,2,&3 and grouped the activities . But find a little confusing to see 3 summary bars at every group intervals
I think there is no solution to this, if you remove “group by summary “ bars in bar format everything goes
This concept is to much confuse. I read the threads in PP and a lot of people got confuse to the point that they thought WBS is the same as grouping by or in P3 WBS is the same as activity code.
This happened also in actual practised. Perhaps we could include this in PP norms. When can we use WBS or when ca we use "grouping by" in MSP or Activity Codes in P3.
In my understanding, we need to review the intent of project management books like PMI Book of Knowledge, maybe some theories from Prince, if ever there is one regarding WBS.
This is a big discussion but I have to go home now. See you next time.
This is really just a clairification. I dont know if you have used the "Group By XXX" function in MSP, but using the word "group" has a very specific meaning (to me, anyway). It really can be very useful and very flexible, but it has a couple of imperfections. One of its best uses is the ability to roll-up the data, such as cost, hours etc. on the visible (filtered) activities only. In the conventional MSP layout, the summary-bar data will show ALL of the data pertinent to all of its sub-tasks, even though you might have a filter applied.
Another excellent use for the Group By function is to convert the conventional MSP programe layout to that of a P3 layout. Moreover, you can formulate "groups" and order them to whatever you so desire. Its one of the best functions that Microsoft has yet introduced.
if you will summarize to level one, level 2 or any lower level in the hierarchy will not be shown.
So it will only be an exercise of futility in the event you want to see only level 2 when you summarize the activity in level one, no way for you to see level 2.
Please could you tell me precisely what you have done so far. Im not sure that I understand. When you say that you are "grouping" the activities, how are you performing this? As far as I can tell, in MSP 2000, you cannot "Group By WBS".
Please expand on your detail, then I could maybe offer some advice.
I assume that you are using the "Group By..." function. If so, then you can Group By..... Column 1 group-name, Column 2 group-name etc, or you can do any combination of the above. However, if you want to exclude specific summary bars, then I believe that you have to filter-out all the activities that reside under that particular summary bar name, and then re-apply the "Group By..." function.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear James
Thanks For Your Interest
But That Does Not Solve My Problem
I Am a Little busy today
let me take some time to reply
Hemanth,
Thanks for your clarification….I understand slightly better (I think).
You’ve created three levels of coding, using “Outline Code” 1, 2 and 3. You have then applied the “Group By …” function to group the data according to Outline Code 1, 2 and 3. You are then trying to summarise and then filter-out certain summary bars. Please tell me if I’m talking rubbish.
Although I’ve almost never really used “Outline Code”, because it doesn’t really do anything for me, I believe that you can “Group By” any of the individual code levels. If you want, you can Group By only Outline Code 1, or Outline Code 2 or Outline Code 3….or any combination of them. If you would then like to “hide” or filter-out only certain summary bars, say, at Outline Code 3, but leave other summary-bars at Level 3, you will have to apply a filter only on those detailed asks that relate to the summary-bar that you would like to remove. If this is what you would like to do, then you can use a “Flag” (yes/no) against each of the detailed task. Apply the “Group By” function, then apply the filter to remove the relevant tasks. This should automatically remove the summary-bars that you wish not to see.
Does this make any sense?
James.
Thank you Mr. James Griffith and Mr. Christian Joseph orbe for valuable comments.
It took some time to reply due to professional commitments.sorry
When I reviewed my original question I found that the question doesn’t reflects what I intended to say.
I beg a pardon
Coming to the problem
I am a P3 user and forced to learn MSP due to third party involvement in a project Who makes plans in MSP
In P3 when we organize activities by WBS or activity code, we can show summary(Or Subtotal ) bar at all levels and have the option to show individual summary bars--- (“summary bar “not summarized bar,which we see when we collapse activities) Bars showing earliest start to latest finish date of group of activities
I was trying to do the same in MSP
I created outline codes 1,2,&3 and grouped the activities . But find a little confusing to see 3 summary bars at every group intervals
I think there is no solution to this, if you remove “group by summary “ bars in bar format everything goes
But I want to retain level2 Or Of Outline code 2
May I hope everyone got the question clearly?
Thanks
[email protected]
Hello James,
Grouping by is different from WBS.
A lot of people got confuse WBS or group by.
This is the same in P3; WBS and activitiy code.
This concept is to much confuse. I read the threads in PP and a lot of people got confuse to the point that they thought WBS is the same as grouping by or in P3 WBS is the same as activity code.
This happened also in actual practised. Perhaps we could include this in PP norms. When can we use WBS or when ca we use "grouping by" in MSP or Activity Codes in P3.
In my understanding, we need to review the intent of project management books like PMI Book of Knowledge, maybe some theories from Prince, if ever there is one regarding WBS.
This is a big discussion but I have to go home now. See you next time.
Regards,
charlie
Charleston,
This is really just a clairification. I dont know if you have used the "Group By XXX" function in MSP, but using the word "group" has a very specific meaning (to me, anyway). It really can be very useful and very flexible, but it has a couple of imperfections. One of its best uses is the ability to roll-up the data, such as cost, hours etc. on the visible (filtered) activities only. In the conventional MSP layout, the summary-bar data will show ALL of the data pertinent to all of its sub-tasks, even though you might have a filter applied.
Another excellent use for the Group By function is to convert the conventional MSP programe layout to that of a P3 layout. Moreover, you can formulate "groups" and order them to whatever you so desire. Its one of the best functions that Microsoft has yet introduced.
Cheers.
James.
Hemanth,
the correction
Hemanth,
WBS organize activities in hierarchical order.
if you will summarize to level one, level 2 or any lower level in the hierarchy will not be shown.
So it will only be an exercise of futility in the event you want to see only level 2 when you summarize the activity in level one, no way for you to see level 2.
regards,
Charlie
Hemanth,
WBS organize activities in hierarchical order.
if you will summarize to level one, level 2 or any lower level in the hierarchy will not be shown.
So it will only be an exercise of futility in the event you want to see only level 2 without showing level 2 in summarizing activities using WBS.
regards,
Charlie
Hemanth,
Please could you tell me precisely what you have done so far. Im not sure that I understand. When you say that you are "grouping" the activities, how are you performing this? As far as I can tell, in MSP 2000, you cannot "Group By WBS".
Please expand on your detail, then I could maybe offer some advice.
James.
Thanks Mr James
But
My Problem is
I have 3 Level Of WBS i want to retain level 2 Summary Bars And delete other two
Cheeers
Hi Hemanth,
I assume that you are using the "Group By..." function. If so, then you can Group By..... Column 1 group-name, Column 2 group-name etc, or you can do any combination of the above. However, if you want to exclude specific summary bars, then I believe that you have to filter-out all the activities that reside under that particular summary bar name, and then re-apply the "Group By..." function.
Have I interpreted your question correctly?
James.