Project Calendars in MS Project

J
Julian Coetzee 👤 Member for 20 years 1 month

Hi Alexandre



Thanks for the comments and reply. At the end of the day that is all one can do, is be careful and try to achieve accuracy. I always want my plan to reflect reality as close as possible.



Kind regards from SA

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello,

Basically, you cannot do anything:

Calendar options are used by MSP to compute how many hours per day / per week, how many days per month a resource available 100% is able to work; e.g. Alexandre is available 100%, he will work 8 hours per day on a 5 day task, that makes a 40 hour workload on this task.

MSP is not very good at managing a project with several task calendars; you should be very cautious when building and checking your schedule.

All the best

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts