Project Calendars in MS Project

J
Julian Coetzee 👤 Member for 20 years

Hi Alexandre



Thanks for the comments and reply. At the end of the day that is all one can do, is be careful and try to achieve accuracy. I always want my plan to reflect reality as close as possible.



Kind regards from SA

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hello,

Basically, you cannot do anything:

Calendar options are used by MSP to compute how many hours per day / per week, how many days per month a resource available 100% is able to work; e.g. Alexandre is available 100%, he will work 8 hours per day on a 5 day task, that makes a 40 hour workload on this task.

MSP is not very good at managing a project with several task calendars; you should be very cautious when building and checking your schedule.

All the best

Alexandre

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts