yes, its not reasonable to assign cost for all weekend for long dur project.
so maybe you can forget about weekend, just assign a overtime work hour for each task , just like you assign resource to each task. (provide where is these overtime is not important to you -- monday nigh or saturday)
Thanks for ypur help I know these but these are all manually I want to know if its possible to adjust at the begining of the project for example it may be a project which has 1 year duration. there is another way in resource information menu in the cost tab you can assign costs for different dates but if your project is long its hard to do that for all weekeds.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
yes, its not reasonable to assign cost for all weekend for long dur project.
so maybe you can forget about weekend, just assign a overtime work hour for each task , just like you assign resource to each task. (provide where is these overtime is not important to you -- monday nigh or saturday)
Thanks for ypur help I know these but these are all manually I want to know if its possible to adjust at the begining of the project for example it may be a project which has 1 year duration. there is another way in resource information menu in the cost tab you can assign costs for different dates but if your project is long its hard to do that for all weekeds.
week end work is considered as overtime work
for a task, you need input overtime work manually.
for example task A start from Fri, dur is 7 days, so finish on Mon next two week, the task span 4 days as week end
the total work is 56hr, dur is 7 day
then you input 16hr of overtime work, then the dur change to 5day, and finish on next Thu.
But you can not specify where is this 16hr, it can be Sat/Sun or night shift of Mon/Tue
the only thing you can sure is the task has a total 16hr of overtime work.
change the view to Resource sheet
select the resource
click resource information button on the standard tool bar
click costs tab
there are A,B,C,D,E 5 sets of cost you can set for the resource
But i think it does not work for set up week end cost
you may try overtime rate in resource sheet for this week end issue