Set up a new task and start changing its type and assigning resources, and I would suggest to go to task usage form instead of gannt, it is on the left side of the screen
make sure you change the task type to fixed duration, then click OK BEFORE you assign additional resources;
MS Project does not compute anything until the OK button has been pushed down;
in other words, if I change the task type from fixed units to fixed duration, then add a 2nd resource, then push OK, MS Project will calculate a fixed units task
Set up the task type as fixed duration will refrain MS P to recalculate the task duration when you add new resources; if you also want that additional resources do not share the amount of work being assigned to the 1st resource working on the task, check out the effort driven box.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Guys...
I found it!!!
Thank you very much!!!
I am planning to continue try and error...
Thanks!! See you guys in another problem...
Regards,
Zureen
Zureen,
Use the online help of the software, you will find comprehensive explanation of the task type and effort driven.
Display the Task Entry view (View, more views ...) to have a Gantt chart and a Task form together.
All the best,
Alexandre
The best advice I can give you:
Set up a new task and start changing its type and assigning resources, and I would suggest to go to task usage form instead of gannt, it is on the left side of the screen
Thank u too Alexandre...
then i know...
help me with the defination please..
fixed units and works?
effort driven?-if i change task type to fixed duration+click an arrow in effort driven box
-if i maintain fixed duration and take off that effort driven error.
what the different?...
oohh Farid..Thank you..
I just tried it and it works!!!
Previous, i just rid off arrow inside the effort driven without looking at task type!! sorry..and thank u so much.
What different if
a) task type = Fix Duration and put
arrow inside effort driven box
b) task type = Fix Duration and take off
that arrow
and What is defination for fixed unit and work?
Zureen,
make sure you change the task type to fixed duration, then click OK BEFORE you assign additional resources;
MS Project does not compute anything until the OK button has been pushed down;
in other words, if I change the task type from fixed units to fixed duration, then add a 2nd resource, then push OK, MS Project will calculate a fixed units task
Alexandre
Are you sure you changed TYPE of the task to fixed duration?
Double click on the task, go to advanced and then to task type.
It is unlikely that this happens because of software
Thank Alexandre and Farid..
Apprecited yer opinion/lesson...
but thats the problem coz i used that effort driven box and it still gave impact to my duration.
Maybe Farid right..it might cause from software problem...
mm..so now..need IT people to give their opinion.is there any possible software can create this problem?
Zureen and Farid sbah el kheir,
Set up the task type as fixed duration will refrain MS P to recalculate the task duration when you add new resources; if you also want that additional resources do not share the amount of work being assigned to the 1st resource working on the task, check out the effort driven box.
Al the best,
Alexandre
Make tasks fixed duration regadless of being effort driven or not.
If your software is OK, the duration should not change