If you created two bars with a finish start relationship - the first bar being the "solid" colour and the second being a lighter shade (in the pattern section), you could then create a summary bar of the two and roll up the bars. On the summary bar you hide the task bar and show the rolled up gantt bars, and on the tasks you roll up the bar to the summary bar. If the second bar was then split into sections, ie breaks between work days, and you put an arrow as the end shape of the second bar, and then minimise the summary bar the results are not too bad. You could aklso add some text to the bar to indicate an ongoing timeframe.
If you want a bar whose color would be stronger to show actual duration and lighter to show remaining duration, go to Format, Bars, then
1. select "Normal" and give it a definite color, bar size and light pattern,
2. do the same thing for "Critical"
This will make it for Remaining duration,
3. select "Actual duration" (or "progress"?), and give it the same color and size that "Normal" and a stronger pattern
4. build a "Progress, Critical" that would be the same as "progress" with a filter on Critical, and give it the same color and size that "Critical" and a stronger pattern.
I tried to do something like this a while back and couldn’t make it work. If you do get hold of something could you post it in this thread, I’d really be interested.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Andrew,
Thanks for that. However, I think that the schedule I am looking at will have so many "work-rounds", it will double the number of activities!!!
Regards.
Tony
If you created two bars with a finish start relationship - the first bar being the "solid" colour and the second being a lighter shade (in the pattern section), you could then create a summary bar of the two and roll up the bars. On the summary bar you hide the task bar and show the rolled up gantt bars, and on the tasks you roll up the bar to the summary bar. If the second bar was then split into sections, ie breaks between work days, and you put an arrow as the end shape of the second bar, and then minimise the summary bar the results are not too bad. You could aklso add some text to the bar to indicate an ongoing timeframe.
Cheers
Andrew
Hello all,
isnt great that the Forum is back!
To fade a task bar does not exist in MS Project.
If you want a bar whose color would be stronger to show actual duration and lighter to show remaining duration, go to Format, Bars, then
1. select "Normal" and give it a definite color, bar size and light pattern,
2. do the same thing for "Critical"
This will make it for Remaining duration,
3. select "Actual duration" (or "progress"?), and give it the same color and size that "Normal" and a stronger pattern
4. build a "Progress, Critical" that would be the same as "progress" with a filter on Critical, and give it the same color and size that "Critical" and a stronger pattern.
It should work the way you want
Alexandre
Hi Tony,
I tried to do something like this a while back and couldn’t make it work. If you do get hold of something could you post it in this thread, I’d really be interested.
Chris Oggham
I am fairly certain this is not a standard feature.
You could paste in a graphic created somewhere else but this is not in my opinion ideal solution..
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au