Work Effort wrong calculations and bars split

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

Do your resources (or any) have a different calendar from the project’s one?.

Spli tasks and dotted / dashed line display a peiod withun the task duration where nobody is at work, possibly due to a non-working day in the resource calendar.

Also check the task info dialog, Advanced tab: does the task use a specific calendar?

have a good Xmas

Alexandre