I don’t recall ever having needed to do this in MS Project, as by default Actual Costs are calculated by the software. However, you may be able to do what you want this way.
Click on the View menu and select Task Usage.
Click on the View menu again, point at Table and click on Cost.
Now click on the Format menu, click on Detail Styles and then select the Usage Details tab.
Hold down CTRL and in the Available Fields list, click on Actual Cost, Baseline Cost and Cost, then click Show, click OK.
Click on the Tools menu, select Options, click on the Calculation tab and uncheck the Actual Costs are always calculated by Microsoft Project check box, click OK.
You will now be able to enter Task Name, Fixed Cost, Actual Cost, and Baseline Cost all of the Cost fields will accept negative values.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dylan,
I don’t recall ever having needed to do this in MS Project, as by default Actual Costs are calculated by the software. However, you may be able to do what you want this way.
Click on the View menu and select Task Usage.
Click on the View menu again, point at Table and click on Cost.
Now click on the Format menu, click on Detail Styles and then select the Usage Details tab.
Hold down CTRL and in the Available Fields list, click on Actual Cost, Baseline Cost and Cost, then click Show, click OK.
Click on the Tools menu, select Options, click on the Calculation tab and uncheck the Actual Costs are always calculated by Microsoft Project check box, click OK.
You will now be able to enter Task Name, Fixed Cost, Actual Cost, and Baseline Cost all of the Cost fields will accept negative values.
Chris Oggham