I guess that this separate fields in both task and resource modes is the cause of the problem.
I can get partial success in either mode by using either the Resource Usage view and grouping by resource group(but this will not allow me to further group by the two work packages that are involved), or by using a task view and grouping by the Work Package ID from the Text field (but where multiple resources are allocated against a task, the grouping will not show a task twice under the respective resource group where two resources are used - it tends to show single resources then "combination" resources).
I suspect that the above makes my situation as clear as mud, but it is the best way of describing the situation that I can think of.
As a final resort, I may be forced to copy the data into Excel and manipulate in there!!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I guess that this separate fields in both task and resource modes is the cause of the problem.
I can get partial success in either mode by using either the Resource Usage view and grouping by resource group(but this will not allow me to further group by the two work packages that are involved), or by using a task view and grouping by the Work Package ID from the Text field (but where multiple resources are allocated against a task, the grouping will not show a task twice under the respective resource group where two resources are used - it tends to show single resources then "combination" resources).
I suspect that the above makes my situation as clear as mud, but it is the best way of describing the situation that I can think of.
As a final resort, I may be forced to copy the data into Excel and manipulate in there!!
there are two set of text fields in MSP,one is for task and another is for resource.
same for other fields eg cost duration,date...
Apologies - working in MSP2000.