The summary bar roll up value of a numeric field is determined by the “Calculation for task and group summary rows” in the Tools, Customize fields form. I would suggest you should use the “Average” option in your case.
I do not think a standard bar may be created to represent this value.
You should be able to create a new bar, say using Start1 and Finish1 fields to represent the % Complete calculated in the new Numeric field by creating a formulae to make Start1 = Start and Finish1 = Duration x the new %Complete, then create a new bar to overlay the summary bar.
Give me a call to discuss if you wish, 04 1118 7701.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
I think you could do something with a Number Field and using the formula function in the Tools, Customize, Fields form.
Probably set the value of the Number Field to equal the Percent Complete and then make the summary equal to the average of the percent complete. It is a bit of messing around but if you keep trying there is a good chance you will get there.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
The summary bar roll up value of a numeric field is determined by the “Calculation for task and group summary rows” in the Tools, Customize fields form. I would suggest you should use the “Average” option in your case.
I do not think a standard bar may be created to represent this value.
You should be able to create a new bar, say using Start1 and Finish1 fields to represent the % Complete calculated in the new Numeric field by creating a formulae to make Start1 = Start and Finish1 = Duration x the new %Complete, then create a new bar to overlay the summary bar.
Give me a call to discuss if you wish, 04 1118 7701.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Paul,
Thanks for your answer. Will such revised % complete for the summary bar be reflected in the progress Line?
Uri Shachar
I think you could do something with a Number Field and using the formula function in the Tools, Customize, Fields form.
Probably set the value of the Number Field to equal the Percent Complete and then make the summary equal to the average of the percent complete. It is a bit of messing around but if you keep trying there is a good chance you will get there.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Why worry, milsetone doesnt contribute any weightage to the overall work progress.
Regards.