Many thanks for all the replies, and particularly for some private assistence from Sukumaran and Tony, I think Ive got this going now, Ill experement a bit more and let you know if I get any more questions!
I dont have MSP-98 to cross check but I am sure that this feature must be available with MSP98 also because this is the basic thing for any planning software. You could check the option and what the rules have been set for calculation.
I think I did exactly what you suggested below, but I didnt get the same result! But Im using project 98 sr1, maybe it didnt work in that version.
What I get is that the tasks split up rather oddly- I get task 3 18th Jul-20th, task 1 on hte 21st, task 2 (complete part) 22-25th (over the weekend), task 1 on the 26th, task 3 on the 27th, task 1 28th-29th, and task 2 1st-2nd Aug !!!
I tried this using your example below, and it worked (MSP2000).
1) Same 3 tasks entered, 4 days duration, start date 18/07/05.
2) Enter % complete for task 2 (I used 50%)
3) I entered the project status date as 21/07/05
3) Go to Tools, Tracking, Update Project, then selected "Reschedule Uncompleted Work to Start After" and the project status date of 21/07/05 was already in there.
4) Once OK was entered, tasks 1 and 3 now start 22/07, finishing 27/07 (includes non-working time at weekend). Task 2 is shown as completed 50% (2 days) on 18+19/07, but the outstanding 50% (2 days work) is shown as being completed 22/07 + 25/07.
Thanks for your reply. I tried this but I could not get a result:
I started a new blank project, and entered unlinked tasks 1, 2, 3 all using resource a, 4 days each.
I set %complete on task 2 to 50% (in reality, tasks may not complete in the planned order)
I went to tools / update task on task 2 - I assume this is not a necessary step, but just another way to set the % complete (I did it by dragging on the task bar)
I went to tools / update project, selected "reschedule uncompleted work... and for entire project, at that point I expect task 2 to change to show 2 days remaining work, and the end date to come forwards by 2 days, but nothing happens.
First you update the task (Tool-->tracking--->update Task)based on % complete or remaining days (whatever you like) then update the project(Tool-->tracking--->update project)click reschedule uncompleted work and give the data date, then click entire project if you to update entire project other wise click selected tasks and then click ok. This will reschedule uncompleted tasks and will show the current expected finish of tasks or project. Hope, I understood correctly what you wanted to do and this will help.
You no need to change the start date of project or any activity.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Many thanks for all the replies, and particularly for some private assistence from Sukumaran and Tony, I think Ive got this going now, Ill experement a bit more and let you know if I get any more questions!
Regards, Ian
Have checked project statistics?Also check the table you are seeing and what kind of dates it is displaying.
good luck
No, I still dont get it:
I started a new project, starting today, 3 tasks, named 1,2,3, all using resource "a" and 1 day each (so the project lasts 3 days).
I set 100% complete for task 2. I go to update project, and set reschedule uncompleted work to start today. Nothing changes in the gantt.
I set % complete for task 2 to 0, then back to 100%. Still nothing changes.
Is it that the estimated end date is shown somewhere else, not on the gantt?
Thanks
Ian,
a) First reset the %complete to 0%.
b) Then again enter %complete for all the task.
Now you will get the estimated project completion date. (I have done a test run on my schedule).
Regards.
Ian,
I dont have MSP-98 to cross check but I am sure that this feature must be available with MSP98 also because this is the basic thing for any planning software. You could check the option and what the rules have been set for calculation.
I think I did exactly what you suggested below, but I didnt get the same result! But Im using project 98 sr1, maybe it didnt work in that version.
What I get is that the tasks split up rather oddly- I get task 3 18th Jul-20th, task 1 on hte 21st, task 2 (complete part) 22-25th (over the weekend), task 1 on the 26th, task 3 on the 27th, task 1 28th-29th, and task 2 1st-2nd Aug !!!
And the end date is still 12 days away!
Any other ideas?
Hi Ian,
Have you reset the Status Date?
I tried this using your example below, and it worked (MSP2000).
1) Same 3 tasks entered, 4 days duration, start date 18/07/05.
2) Enter % complete for task 2 (I used 50%)
3) I entered the project status date as 21/07/05
3) Go to Tools, Tracking, Update Project, then selected "Reschedule Uncompleted Work to Start After" and the project status date of 21/07/05 was already in there.
4) Once OK was entered, tasks 1 and 3 now start 22/07, finishing 27/07 (includes non-working time at weekend). Task 2 is shown as completed 50% (2 days) on 18+19/07, but the outstanding 50% (2 days work) is shown as being completed 22/07 + 25/07.
Hope this helps.
Thanks for your reply. I tried this but I could not get a result:
I started a new blank project, and entered unlinked tasks 1, 2, 3 all using resource a, 4 days each.
I set %complete on task 2 to 50% (in reality, tasks may not complete in the planned order)
I went to tools / update task on task 2 - I assume this is not a necessary step, but just another way to set the % complete (I did it by dragging on the task bar)
I went to tools / update project, selected "reschedule uncompleted work... and for entire project, at that point I expect task 2 to change to show 2 days remaining work, and the end date to come forwards by 2 days, but nothing happens.
What am I missing?
Thanks
Ian,
First you update the task (Tool-->tracking--->update Task)based on % complete or remaining days (whatever you like) then update the project(Tool-->tracking--->update project)click reschedule uncompleted work and give the data date, then click entire project if you to update entire project other wise click selected tasks and then click ok. This will reschedule uncompleted tasks and will show the current expected finish of tasks or project. Hope, I understood correctly what you wanted to do and this will help.
You no need to change the start date of project or any activity.