Progress line in MSP

F
Frans Lasut 👤 Member for 19 years 11 months

Hi, I’m experienced P3 user but currently using MSP.



I have a question about progress line.



I have a task that has not started yet. Its baseline start date (I had already saved the baseline) is June 10th, 2006. After rescheduling (The project status date is June 14th, 2004), its forecast start date becomes June 24th, 2006



In my opinion (as P3 user), the task is only delayed for 4 days. But, when I displayed the progress line in relation to baseline line, why it told me that the task is delayed for more than 2 months?



How could this situation occur??



Please advise

E
Ewald Langezaal 👤 Member for 20 years 11 months

Thanks for your swift reply, it is working now, indeed I forgot to reset the % complete and fill it out again.



I think MSP is still a Mickey Mouse program

S
Sukumaran Subaramaniyan 👤 Member for 21 years 3 months

Ewald,



What you need to do is once you tick the command, go back to Gantt Chart/Tracking Gantt and change the percentage to 0%. After that re-type the progress percentage. Now you can see the progress line shows progress ahead of the schedule.



Actually the command is funtioning. You just need to do some test run.



Regards.

J
Jaco Stadler 👤 Member for 21 years 8 months

Hi Ewald



I Assume you are Using Remaining Duration & % Complete.



If Not Try It. I Have just run a test and it is Working

J
Jaco Stadler 👤 Member for 21 years 8 months

Hi Ewald



Try



1) Save a Copy (Always save a Copy)

2) Tools / Options

3) Tab Called Calculation

4) Tick Edit to Total Task % >>>>>>> to Status Date.



This Should do it




Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts