BCWS at Task Level not calculating
Forum Sponsor
Top Posters
Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
Colleen,
Have set the status-date, via Project>Project Information?
James.
Work around
Buy a program that works properly, get yourself trained in Earned Value not just how to use MSProject
Distrust absolutely any cost calculations done by MSProject
I will train you just email me [email protected]
Regards
tom