You must remember to save to mpx. A further problem, is that MSP does not have code structures, so you have to go through the excercise of putting in the headings, or indents, or whaever they call it, It is a painful excersize, but at the end of the day if that is what they want, deliver. Give me a shout if you are struggling
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Jose,
Consider just exprt the necessery information from P3 into DBF. Then import it into MSP.
The painful process is activity ID re-numbering, not the others.
Also consider import that MPX into MSP 95 version and then save it into MPP for MSP2002
Hi jose,
Porco Karelio
You must remember to save to mpx. A further problem, is that MSP does not have code structures, so you have to go through the excercise of putting in the headings, or indents, or whaever they call it, It is a painful excersize, but at the end of the day if that is what they want, deliver. Give me a shout if you are struggling
What happens AFTER the message has displayed?
Does the process stop or ocntinue with additional error messages?
Thanks Alexandre
The export facility to MPX is the one built inside the P3 it self. I have no control on the field that P3 exports.
THe version of MS Project is 2002, and I tryed to use the standard open file choosing type MPX. Also no control about the way MS project imports.
Hello,
What version of MSP are you using?
Is it in the same language as P3?
How long is your P3 project, how many tasks? Did you export the time and hour for the date fields?
MS Project is not smart in using MPX files, and do not understand everything P3 or any other planning software which is able to export to MPX files.
All the best
Alexandre Faulx-Briole