More specifically, you cannot link the same several project files with several resource files (pools); on the other hand, there is no limit to the nunmber of project files you can link to one single resource file.
To use the "resource group" field in the resource sheet, or to use the resource breakdown structure in the custom fields is the best answer to your needs.
Due to the way MSP generates assignments you can only share resources between two project files at any time.
If you had one resource pool, and used the "Resource group" field, when you come to work on your plans you could then filter on the resources you want to see, either by using the drop down menu in the resource view or when using the "Assign Resources" box check the "Resource list options" and use the filter options to view the relevent resources.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello there,
More specifically, you cannot link the same several project files with several resource files (pools); on the other hand, there is no limit to the nunmber of project files you can link to one single resource file.
To use the "resource group" field in the resource sheet, or to use the resource breakdown structure in the custom fields is the best answer to your needs.
Regards,
alexandre
Due to the way MSP generates assignments you can only share resources between two project files at any time.
If you had one resource pool, and used the "Resource group" field, when you come to work on your plans you could then filter on the resources you want to see, either by using the drop down menu in the resource view or when using the "Assign Resources" box check the "Resource list options" and use the filter options to view the relevent resources.
Hope this helps.
Will