"SS+Lag" or "FF"

R
Raj Maurya 👤 Member for 22 years

Activity finish is more important to deliver the project in time so better to use FF and take care of lag (counting as per default caleneder as Bernard said). But there is no harm to use SS with lag to keep Project Managers happy.

B
Bernard Ertl 👤 Member for 23 years 8 months

You may want to do some testing with lags and MS Project if you are using multiple calendars. You may get unexpected results. It appears to use the default project calendar for lags irrespective of the calendars for the tasks being connected by the relationship.



Bernard Ertl

eTaskMaker Project Planning Software

Featured Partner