Please do the following to find what is the wrong.
1)Open sub project Check the Project Overview & sse that completion of Sub project will not be same as Master project.
2)Take filter for Float Less than 2 & check the Link for Crtical path Where are brocken in sub project. if You using different calender for some activity they also Crtical Path not shown from Begining.
Sorry to replying late as I was very busy. I had my one master schedule with different subproject and a common resource library. In that fortunately the critical paths of subproject and Master project was same and that was needed to.
For your case to see the different critical path, I guess if you impose subprojects finish date constraint then you would be able to find the CP for subprojects.
Multiple critical path check box works to show CP more than one if you have different path open ended with different finish dates. Then It will show CP based on defined slack.
1- What exactly I need: A critical path for a subproject, when I need to work with it independent from the master project. Imagine its being done with a different group and in a different location than other subprojects. The critical activities shown are just same as master project. It doesnt recognize critical path/tasks for each subproject, when we need to consider it independnetly.
Why I need it separately? Because the team/location of each subproject is totally independent. They are not interested in other subprojects (Program manager is responsible for that). They need to see relational float within their own project. e.g. what can delay their colleagues jobs (same team).
2- When I open a sub-project independently, the critical path/activities shown is just Master Projects critical path. It doesnt show the subproject critical activities. Please give it a try and let me know if you experience differently. To MSP, the whole master project has just one goal and one critical path (which passes through some/all subprojects). It cant understand an independent character for a subproject and doesnt calculate a critical path for a subproject. In an independently opened subproject, MSP only shows critical tasks which are critical for the master project!
3- Multi-critical path checkbox in calculation tab is for a different purpose, although its name sounds to be more useful. It just pushes (makes critical) successor-less tasks to the latest possible time. It never helps anything about sub-project critical path. To be honest, I never found a real use for it! Maybe for resource leveling.
Thanks
Nozar
PS: Does my request from MSP make sense? Anybody struggled it before?
What you exactly wants? To show critical path in subproject while its opened alone? or when it opened with Master project? I think you can try with Option then click calculation tab and then Multiple crical paths.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hello Nazer,
Please do the following to find what is the wrong.
1)Open sub project Check the Project Overview & sse that completion of Sub project will not be same as Master project.
2)Take filter for Float Less than 2 & check the Link for Crtical path Where are brocken in sub project. if You using different calender for some activity they also Crtical Path not shown from Begining.
Good Luck
Nozar,
Sorry to replying late as I was very busy. I had my one master schedule with different subproject and a common resource library. In that fortunately the critical paths of subproject and Master project was same and that was needed to.
For your case to see the different critical path, I guess if you impose subprojects finish date constraint then you would be able to find the CP for subprojects.
Multiple critical path check box works to show CP more than one if you have different path open ended with different finish dates. Then It will show CP based on defined slack.
Hello Raj and thanks for your reply.
1- What exactly I need: A critical path for a subproject, when I need to work with it independent from the master project. Imagine its being done with a different group and in a different location than other subprojects. The critical activities shown are just same as master project. It doesnt recognize critical path/tasks for each subproject, when we need to consider it independnetly.
Why I need it separately? Because the team/location of each subproject is totally independent. They are not interested in other subprojects (Program manager is responsible for that). They need to see relational float within their own project. e.g. what can delay their colleagues jobs (same team).
2- When I open a sub-project independently, the critical path/activities shown is just Master Projects critical path. It doesnt show the subproject critical activities. Please give it a try and let me know if you experience differently. To MSP, the whole master project has just one goal and one critical path (which passes through some/all subprojects). It cant understand an independent character for a subproject and doesnt calculate a critical path for a subproject. In an independently opened subproject, MSP only shows critical tasks which are critical for the master project!
3- Multi-critical path checkbox in calculation tab is for a different purpose, although its name sounds to be more useful. It just pushes (makes critical) successor-less tasks to the latest possible time. It never helps anything about sub-project critical path. To be honest, I never found a real use for it! Maybe for resource leveling.
Thanks
Nozar
PS: Does my request from MSP make sense? Anybody struggled it before?
What you exactly wants? To show critical path in subproject while its opened alone? or when it opened with Master project? I think you can try with Option then click calculation tab and then Multiple crical paths.