Maintenence schedule
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Raj
Thanks. Ill give it a try.
Regards, Gerry
There is one way is that update the activities but dont reschedule the balance work. Other way is define activity as fixed duration and put end date contraint and define the expected work(in hour or so) to be done during the whole period of work. So when ever you will update resource unit will fluctuate but duration will remain constant. Try this, hopefully it will work.