In summary MSP calculates effectively in hours and then uses the factors entered in on bottom of the form found under Tools, Options, Calendar tab to calculate the months. This value has nothing to do with a calendar. So when you enter a duration in months it uses these factors to calculate hours and schedules the task over the applicable calendar ignoring the number of days in a month.
There are therefore a number of solutions such as removing some days from the long months or reducing the number of hours per day on long months but they are all work arounds and difficult.
The other option as suggested by David Bordoli is to find something else such as P3 which allows time units of months or if the schedule is small I usually put it into Excel with some formulae for logic etc.
You will find most financial Budgeting software will work in months but does not have the capability of developing a network.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
I just tried it. I tried to enter 1 month as a duration and it seemed to just put in 4 weeks. Then I tried 1 emonth (elaspsed) and that seemed okay for 1 January to 31 January but when I moved the start dat it seemed to hang on to 31 days.
I dont know if any of the experts can help you, I tried the help files (which wernt much help!).
It doesnt assist you I guess but Powerproject works quite well on this, in both month and elaspsed month modes.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks a lot guys!
Thats what I thought :-(
I suppose I will have to find another way to do it.
Have a nice day,
Isabelle
Isabelle
You do have a problem with this one.
In summary MSP calculates effectively in hours and then uses the factors entered in on bottom of the form found under Tools, Options, Calendar tab to calculate the months. This value has nothing to do with a calendar. So when you enter a duration in months it uses these factors to calculate hours and schedules the task over the applicable calendar ignoring the number of days in a month.
There are therefore a number of solutions such as removing some days from the long months or reducing the number of hours per day on long months but they are all work arounds and difficult.
The other option as suggested by David Bordoli is to find something else such as P3 which allows time units of months or if the schedule is small I usually put it into Excel with some formulae for logic etc.
You will find most financial Budgeting software will work in months but does not have the capability of developing a network.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au
Hello Isabelle
:-(
I just tried it. I tried to enter 1 month as a duration and it seemed to just put in 4 weeks. Then I tried 1 emonth (elaspsed) and that seemed okay for 1 January to 31 January but when I moved the start dat it seemed to hang on to 31 days.
I dont know if any of the experts can help you, I tried the help files (which wernt much help!).
It doesnt assist you I guess but Powerproject works quite well on this, in both month and elaspsed month modes.
David