Make sure your status date is correct in the -->Project -->Project Information Form, in this case 22/11.
To schedule your activities you have to go to --> Tools --> Tracking --> Update Project -->Reschedule uncompleted work to start after 22/11.
I always have the tracking toolbar open. It is then very easy to reschedule/ progress single or a selection of tasks.
Remember to always put in actual start and finish dates. The easiest way is to open up a collumn or go to --> Views --> More Views and select the Task Details Form.
Updating the Task with MSP is bit different than P3 thats why you are facing this problem. In MSP there are two types of progress caculation and ie % complete and % work complete. Based on your requirement you can use either. % complete simple calculates based on duration for eg if you have a activity of 10 day duration if you put 1 day actual it will show 10% complete or if you say its 50% complete it will show up to half of the bar. The second one is based on your based on the efforts that is required to complete the task no matter how many days over, if you say a resource needed to work 10 days to complete the work and after 2 days of his actual working it will show 20% work completed. I hope this will help you a little bit to show your progress data.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Yeh, I agree with getting a real scheduling package, only in this case, it is the contractor who is utilising MSP, I am only verifying the progress.
It also seems that on has to make use of the task splitting facility in MSP, there is a thread with regards to this located elsewhere in PP.
Anyway, I since have corrected this and found the schedule to be roughly 27d negative, now, how am I to rid myself of this....
I wonder.
Hi Ronald,
Make sure your status date is correct in the -->Project -->Project Information Form, in this case 22/11.
To schedule your activities you have to go to --> Tools --> Tracking --> Update Project -->Reschedule uncompleted work to start after 22/11.
I always have the tracking toolbar open. It is then very easy to reschedule/ progress single or a selection of tasks.
Remember to always put in actual start and finish dates. The easiest way is to open up a collumn or go to --> Views --> More Views and select the Task Details Form.
Get a real scheduling package.
Regards,
Erik Jonker
It could have been worse, it could have been 30d negative.
But dont worry, the contractor got himself in trouble - he can get himself out of trouble.
Regards,
Erik
Hi! Ronald,
Updating the Task with MSP is bit different than P3 thats why you are facing this problem. In MSP there are two types of progress caculation and ie % complete and % work complete. Based on your requirement you can use either. % complete simple calculates based on duration for eg if you have a activity of 10 day duration if you put 1 day actual it will show 10% complete or if you say its 50% complete it will show up to half of the bar. The second one is based on your based on the efforts that is required to complete the task no matter how many days over, if you say a resource needed to work 10 days to complete the work and after 2 days of his actual working it will show 20% work completed. I hope this will help you a little bit to show your progress data.