View Layout by WBS

R
Raj Maurya 👤 Member for 22 years

WBS in MS-P is not similar to P3 of you want to organise based on WBS then you have to do some manual work. Create custom WBS based on WBS created by MSP itself. On that custon WBS you can sort/filter/group the activities as per you need. In other way of doing similar work you can follow Alaxandre’s suggestion. But rememeber it is not something like P3 WBS.

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

MS-P displays the outlined (hierarchical) layout by default; to set it up if necessary, go to Tools, Options, View, Demote (or Outline ?) in the lower part of the Dialog box.

If you want to display another hierarchy, you will have to group the tasks (similar to Organize in P3):

Go to Project, Group by; define any group criteria you need and click OK

The Gantt Chart will be reorganized about the same way as P3 would do.

Alexandre Faulx-Briole

P
Paul Harris 👤 Member for 25 years 3 months

I don’t think there is.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

L
Luca Basile 👤 Member for 23 years

I am not sure this is what you are looking for.

In any case, in Filter select

Top level task or Summary task.

It is not yet like P3.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts